After years of championing renewable energy, major tech companies are beginning to realize that it may not meet their ...
The cooling towers of the Susquehanna Steam Electric Station, majority-owned by Talen Energy. (Will Parson/Chesapeake Bay ...
Nuclear plant owner Talen Energy Corp. says an initial 300 MW of data center development can proceed despite feds' rejection of grid link agreement to its Susquehanna facility in Pennsylvania's ...
Axios reported today that Amazon’s project recently failed to secure a key regulatory approval. Meta’s planned data center campus, in turn, is said to have raised environmental concerns.
The proposal aimed to revise an ISA involving PJM, the regional grid operator, Susquehanna Nuclear, which owns the power plant, and transmission owner PPL Corp. The amendment would boost the data ...
Last May, the tech giant secured a nuclear-powered data center in Pennsylvania to leverage clean energy from the Susquehanna ...
A potential nuclear power supply deal for a Meta artificial intelligence (AI) data center was obstructed by the discovery of ...
No deficiencies were found in a recent regional simulation of a nuclear power plant disaster, said David Elmore, Luzerne County deputy director of emergency services.
The Federal Energy Regulatory Commission has dealt a blow to plans by e-commerce and technology giant Amazon to build a ...
Processing artificial intelligence (AI) queries consumes 300% to 400% more electricity than normal searches. The need to ...
In fact, Amazon.com already received such an exemption in 2015. A data center at the Susquehanna nuclear power plant in ...
The denial of a power agreement tied to Amazon Web Services' nuclear data center campus could slow a potential wave of ...